Alasdair’s Engineering Pages © A. N. Beal 2025 www.anbeal.co.uk
www.anbeal.co.uk
The Structural Engineer, Vol. 8 No. 2, 21st January 2003
CDM and site safety -
Alasdair Beal
The Construction (Design and Management) Regulations first appeared in 1994. Although they have failed significantly to reduce injuries and deaths on building sites, they now form a well-
The Introduction to the ACOP claims that ‘the Code has a special legal status. If you are prosecuted for breach of health and safety law, and it is proved that you did not follow the relevant provisions of the Code, you will need to show that you have complied with the law in some other way or a Court will find you at fault’.
The legal basis for this claim is not clear -
In this situation, engineers would do well to look rather carefully at what the ACOP says and remember that its words are not intended just as friendly advice -
Prohibited materials
The CDM Regulations ask designers to take account of health and safety issues in their designs but they do not ban the use of particular materials and construction methods. However, if the new ACOP is held to have the force of law, some of its clauses could change all this. Examples are listed below (with emphasis added).
Cl. 127: The designer should, where possible: ...
(b)design out health hazards, e.g.:
* specify less hazardous materials, e.g. solvent-
* avoid processes that create hazardous fumes, vapours, dust, noise or vibration, including disturbance of existing asbestos, cutting chases in brickwork and concrete, scabbling concrete, breaking down cast in situ piles to level, hand digging tunnels;
(c) design out safety hazards, e.g:
* fragile roof materials;
* materials that could create a significant fire risk during construction;
(g) design to simplify future maintenance and cleaning work, e.g:
* specify windows that can be cleaned from the inside.’
Remember the ACOP’s claims of ‘special legal status’ and look again at the words which start Clause 127: ‘The designer should, where possible...’. If this means anything, it means that these are recommendations which must be complied with in all cases except where it is not possible to use alternatives. If this clause is taken to have the force of law, it would effectively make some common materials and methods of construction illegal (See Table 1).
Table 1: Material which could be banned
These are only examples and no doubt more could be identified. However they illustrate the profound effect this ACOP clause could have on manufacturers and materials suppliers. Maybe some people will agree with banning materials and items on the above list, but if this is the HSE’s intention, why does it propose to prosecute only the designers who specify them? Why is there to be no action against the companies which manufacture and sell these items, or the contractors who buy and use them? Conversely, if the HSE does not intend there to be a ban on the use of these items in the construction industry, what exactly is Cl. 127 of the ACOP intended to mean?
Design and risk
Clause 113 of the new ACOP says: ‘Under CDM designers must ensure that any designs they prepare for the purposes of construction avoid risks to anybody carrying out construction or cleaning work... on or in the structure at any time...’
This is a major change from the CDM Regulations, which say:
‘Every designer shall:...
(a) ensure that any design he prepares and which he is aware will be used for the purposes of construction work includes among the design considerations adequate regard to the need:
(i) to avoid foreseeable risks to the health and safety of any person at work carrying out construction work or cleaning work in or on the structure at any time ...’ (emphasis added).
One does not need to be a lawyer to see that the differences between the two documents are significant: a requirement that designers should ‘include among the design considerations adequate regard to the need’ is changed to ‘designers must ensure’ and the requirement that there should be ‘adequate regard to the need to avoid foreseeable risks’ changes to a requirement that that ‘any designs they prepare ... avoid risks’.
It is not clear at all what Courts will make of this situation: will they hold that where there is a conflict between the ACOP and the Regulations, the latter must take precedence, or will they hold that the ‘special legal status’ claimed for the ACOP allows its provisions to effectively supersede the Regulations?
Designers who have complete confidence that judges can always be relied on to stick to the letter of the law may not be unduly worried about all this. However, for those who believe (or fear) that the Courts might be tempted to entertain extending the law along the lines outlined in the ACOP, it is not so easy. They may find themselves rereading those words in clause 113 and wondering what they actually mean. ‘Designers must ensure’ is clear enough -
The most fundamental problem is that a building site is a dangerous place and a designer can only influence what happens on it to a limited extent. The degree of risk depends critically on the quality of the contractor’s site management and the skill of the people employed. Under ACOP Cl. 113 do designers have to create designs which ‘avoid’ risks on the assumption that the work will be carried out by competent, well-
Responsibility for temporary works
Under the terms of most designers’ appointments and most construction contracts, the designer is only responsible for the design of permanent works. The choice of method of construction, the design of any temporary works required and the stability of the structure during construction are all firmly established as the responsibility of the contractor, not the designer. This is a long-
The CDM Regulations respect this division of responsibility, only requiring the designer to provide ‘adequate information’ to the contractor about any aspect of the design which might affect the health and safety of people building it (Regulation 13 (2 (b)).
Regulation 13 (3) confirms that details are required ‘of only the matters referred to therein, to the extent that it is reasonable to expect the designer to address them at the time the design is prepared, and to the extent that it is otherwise reasonably practicable to do so’.
The new ACOP respects this to some extent: Cl. 136 acknowledges that ‘Under CDM, designers are not required to ... specify construction methods ... or exercise health and safety management function over contractors’. However some of the requirements in other clauses suggest a quite different approach:
Cl. 127: ‘The designer should, where possible:...
(f) provide lifting points and mark the weight, and centre of gravity of heavy or awkward items requiring slinging both on the drawings and on the items themselves’
Cl. 132: ‘Examples of significant hazards where designers always need to provide information include: ...
(b) temporary works, required to ensure stability during the construction, alteration or demolition of the whole or any part of the structure, e.g. bracing during construction of steel or concrete framed buildings’.
Most designers of steel-
It is not clear precisely what ‘information’ is supposed to be provided by the designer about temporary works in ACOP Cl. 132 (b). Depending on how this is interpreted, it could be deemed effectively to transfer responsibility for temporary works design from the contractor to the designer. Indeed the clause as written goes further than this, requiring the designer to also provide ‘information’ about the temporary works required for any possible future alterations and even for the eventual demolition of the structure (presumably with alternatives provided for either its altered or unaltered states). Clearly any such moves potentially could involve design engineers in a large amount of additional work and impose serious additional liabilities on them.
The legal basis of this clause appears to be weak: there are no corresponding requirements in the CDM Regulations and a requirement for designers to design temporary works for possible future alterations and also demolition is clearly unreasonable and contravenes the terms of Regulation 13 (3). It is also obviously completely impractical to expect a designer to specify the temporary works required for construction when s/he has no knowledge of (or control over) the contractor’s chosen construction method.
Nonetheless this Clause must be taken seriously: as noted already, ‘special legal status’ is claimed for this ACOP and the HSE has already tried once to prosecute a designer for the collapse of a steel frame during erection. On that occasion, the judge threw the case out but if provisions of the new ACOP were to be accepted as legally binding by the Courts, and they interpreted the requirement for ‘Information’ in an onerous way, design engineers could find themselves saddled with responsibility for designing temporary works on all their contracts.
There are many good reasons for resisting any move in this direction. For a start, it would impose on designers a duty to carry out work which no one has appointed them to do -
A move to make designers legally responsible for the design of temporary works on the projects they work on would require a major retraining programme for structural engineers. Standard building and professional contracts and professional indemnity insurance policies would also need to be rewritten -
If this is what ACOP Cl. 132(b) is intended to mean, then the HSE really should say so clearly, seek the necessary legal backing for the change -
Setting a bad example
To assist interpretation of the CDM Regulations, the ACOP includes examples of how they may be applied in practice. Unfortunately, copying some of these could lead to very unfortunate conclusions. In Example 24, a warehouse owner decided to carry building work by employing various contractors directly and appointing a project manager to coordinate and manage them. He then took on the role of Principal Contractor himself. In Example 35, a pharmaceutical company appointed itself as Principal Contractor for commissioning a new process plant.
However, according to CDM Regulation 8 (3), ‘no person shall arrange for a contractor to carry out or manage construction work unless he is reasonably satisfied that the contractor has the competence to carry out or, as the case may be, manage, that construction work’ and Regulation 6 (2) states: ‘The client shall not appoint as principal contractor any person who is not a contractor’. Both the warehouse and the pharmaceutical company appear to have contravened Regulation 6(2). Any other company which took the advice of the ACOP and followed in their footsteps could end up in serious trouble. How did these examples find their way into the ACOP as ‘illustrating good practice’?
Conclusions
Depending on how they are interpreted, some clauses in the new ACOP for the CDM Regulations could have major effects on the construction industry and on design engineers. This follows from the way the ACOP has been drafted and the special legal status which is claimed for it.
There is no problem where it only reaffirms or clarifies the provisions of the existing CDM Regulations. However, some of the ACOP clauses introduce wording which appears to change what is said in the Regulations, and others introduce new requirements which do not appear in the Regulations at all. As the HSE has signalled its intention to use the new ACOP as the basis for prosecuting designers after site accidents, it is important that the legal status and precise meaning of some of its clauses are clarified as a matter of urgency.
References
1. ‘Designers face clamp down after safety blitz’, New Civil Engineer, 16 May 2002
|
Possible banned materials/items |
Comments |
|
Solvent- |
In most situations it is possible to substitute a water- |
|
Standard epoxy adhesives, grouts, paints etc. |
In most situations it is possible to substitute non- |
|
Cutting chases in walls |
It is almost always possible to place cables etc. in surface- |
|
Fibre- |
It is almost always possible to subsiute alternatives such as steel profiled sheeting which are not fragile |
|
Polystyrene and other inflammable insulation materials |
It is usually possible to substitute a less inflammable or non- |
|
Standard synthetic roof sarking felts |
It is always possible to substitute less inflammable alternatives (though these tend to be more expensive) |
|
Timber- |
When there is a fire on a building site, timber is almost always involved - |
|
Fixed- |
It is always possible to specify the alternative of an opening window which can be cleaned from the inside |
Table 1: Materials which could be banned
The original copy of this paper is available from